 BOMBING RANGE ROAD PHASE 8 PROJECT UPDATES:

August 17, 2018 Project Update:

The Contractor installed stormwater piping and the sewer main extension the week of August 13th.  The Contractor will continue to work on stormwater piping and will begin work on the new water main along with the preparation for the new sidewalk the week of August 20th.

August 9, 2018 Project Update:

The City has hired Total Site Services to complete the construction on Bombing Range Road Ph 8.  The Contractor started work on August 6th. Bombing Range Road will be closed to all through traffic from August 9th to mid October.  The Contractor will be installing new water main, storm drainage facilities, cur, gutter, sidewalk and street lights as part of this project.  New asphalt overlay will be completed the length of this project as well as portions of Dallas Road From Kennedy Rd to Arena Rd.

BROTHERHOOD RESERVIOR AND TRANSMISSION MAIN PROJECT UPDATES:

August 17, 2018 Project Update:

The Contractor continued the installation of the new water main along the south side of SR224 from N. 62 Ave towards the BREA office. The Contractor will continue installing the water main heading east towards N. 58th Place the week of August 20th.  Work may involve intermittent traffic delays on SR 224.  Please drive with caution through the project.

July 27, 2018 Project Update:

The City’s contractor has extended the new watermain from N.69th to 62nd and worked on new sewer services. The Contractor will continue to work on sewer services requiring one lane closures on SR224. Waterline work will continue along the south side of SR224 east of N.62nd Ave and N.58th Place.

The Brotherhood Reservoir and Transmission Main projects will begin construction July 2018.

The Contractor has begun the water line installation between N 69th Ave and 62nd Ave.  The Contractor has scheduled a water shut down for the homes located in the Desert View Mobile home park south of SR 224 to remove a section of old water pipe during the installation for the new water main.  The Contractor will continue work along SR224 between 62nd Ave and Grosscup Blvd in the weeks to follow.  Work involves installation of new sewer services to lots on the south of SR224. This work requires crossing SR224 and will have impacts to traffic.  These impacts can be expected over the next several weeks.  You can expect to see SR224 reduced to one lane traffic controlled by a traffic control flagger.  Short delays should be expected.

  S. 38TH AVE / MT. ADAMS VIEW DRIVE PROJECT UPDATES:

August 17, 2018 Project Update:

The Contractor finished the  roadway subgrade, installed base rock on Mt. Adams View Drive and is working on subgrade and base rock on S. 38th Ave between Mt. Adams View and Northlake. The Contractor experienced a slight set back when an un-located irrigation main was hit on Wednesday but was quickly shut off and no damage to private property occurred. The City is currently working on a fix to lower the irrigation main to eliminate the conflict. The Contractor will continue working on subgrade and base rock on S.38th south of Mt. Adams View the week of August 20th. Current project schedule indicates the week of August 27th the Contractor will begin working on subgrade on S 38th Ave. north of Mt. Adams View Drive. During these activities there may be short durations of rough road conditions and heavy equipment present.

Please drive slowly and with caution for your safety and the safety of the workers.

August 9, 2018 Project Update:

The Contractor has finished the installation of the drywells and catch basins on the south end of S 38th Ave this past week and have started working on the subgrade on Mt Adams View Drive. The Contractor is scheduled to continue grading subgrade on Mt Adams View Drive the week of August 13th and also begin laying base rock.  The Contractor will than move to blading and compacting subgrade and placing base rock on S 38th Ave between Mt Adams view and Northlake. The City asks that drivers try to take an alternate route avoiding the active construction equipment if possible.

July 27, 2018 Project Update:

The contractor installed utility conduit crossings the week of July 23,2018. The week of July 29, 2018 the contractor will begin working on catch basins and drywells on the south end of S.38th near Northlake Drive. Roadway grading is expected to start on Mt. Adams View Drive the week of August 8, 2018.

The City has hired Tapani, Inc. for the construction of the S. 38th Ave / Mt Adams View Drive project.  Construction is expected to begin July 16, 2018. The Contractor will be constructing the project in sections to reduce the overall impacts to residents.  The Contractor will begin with removing and relocating fences, clearing and grubbing vegetation, installing utility crossings, and storm drywells.  Towards the middle of August the Contractor will begin grading the roadway subgrade on Mt. Adams View followed by the placement of rock to help with the extended rough road conditions. They will then proceed to the southern end of S. 38th Ave between Mt. Adams View and Northlake Dr. followed by the northern portion of S. 38th Ave between Cherry Hills and Mt. Adams View.  The current project schedule has the roadways being rocked and ready for pavement by the end of September with paving scheduled for the first week of October.  Please remember the schedule is subject to change once construction is under way.

If you have specific questions about this project, please contact West Richland Public Works at (509)967-5434.