S.38th/Mt Adams View Drive Project Updates:

October 19, 2018

The Contractor will continue to clean up landscaping, patch adjustments, and clean up ditch line and culvert crossings.

Please drive slowly and with caution for your safety and the safety of the workers.

July 16, 2018 Project Update:

The City has hired Tapani, Inc. for the construction of the S. 38th Ave / Mt Adams View Drive project.  Construction is expected to begin July 16, 2018. The Contractor will be constructing the project in sections to reduce the overall impacts to residents.  The Contractor will begin with removing and relocating fences, clearing and grubbing vegetation, installing utility crossings, and storm drywells.  Towards the middle of August the Contractor will begin grading the roadway subgrade on Mt. Adams View followed by the placement of rock to help with the extended rough road conditions. They will then proceed to the southern end of S. 38th Ave between Mt. Adams View and Northlake Dr. followed by the northern portion of S. 38th Ave between Cherry Hills and Mt. Adams View.  The current project schedule has the roadways being rocked and ready for pavement by the end of September with paving scheduled for the first week of October.  Please remember the schedule is subject to change once construction is under way.

 If you have specific questions about this project, please contact West Richland Public Works at (509)967-5434